PROJECT PROFILE SUMMARY

Client 
Bechtel International (Atlantic LNG)

Project
15 MTPA output of LNG

Scope

  • Installation of mechanical equipment and piping erection
  • Piping pre-fabrication & installation
  • Construction of firewater tanks
  • Straight-run piping
  • Pre-fabrication and Installation of pipe spools
  • Installation of structural steel
  • Installation of static and rotating equipment
  • Civil works and foundations (subcontract)
  • Electrical & Instrumentation (subcontract)
  • Pre-commissioning support
Year Man-Hrs  US$
Train 4 2006   3,200,000   53,385,423
Train 2&3 2001   2,500,000   51,247,144
Train 1 1998   1,500,000   14,516,113